Chapter 6 homework

Chapter 6 Homework 6. 9. LEAD TIME Lead-time is a time gap between starting of a process and completion of scheduling and manufacturing operations of various products. Manufacturing lead-time is time taken from manufacturing to purchase of products made by customers. It consists of four processes that include preprocessing, processing, fixed and variable time. Preprocessing lead-time is the time required to generate work order from the time of requirement of various products. Processing time is the time taken to manufacture the various items or products. Fixed lead-time is the part of processing time, which is not variable according to the order of quantity. Variable lead-time is the part of processing time, which is dependable on the order quantity. Manufacturing lead-time is the summation of preprocessing, processing and post-processing lead-time (ORACLE, “ Oracle Bills of Material Users Guide”).
CALCULATION OF MANUFACTURING LEAD TIME OF WORK CENTER 10 FROM SETUP A MACHINE
Setup on A = 50 minutes is the preprocessing time
Processing time is the move time between operations i. e. 30 minutes
Post-processing time is the run time of A = 5 minutes per piece
Lot size = 75
Total post-processing time = 5 x 75 = 375
Manufacturing lead-time = preprocessing time + processing time + post-processing time
= 50+30+375
= 455 minutes
Source: (ORACLE, “ Oracle Bills of Material Users Guide”)
CALCULATION OF MANUFACTURING LEAD TIME OF WORK CENTER 10 FROM SETUP B MACHINE
Setup on B = 100 minutes is the preprocessing time
Processing time is the move time between operations i. e. 30 minutes
Post processing time is the run time of B = 7 minutes per piece
Lot size = 75
Total post processing time = 7x 75 = 525
Manufacturing lead-time = preprocessing time + processing time + post processing time
= 100+30+525 = 655 minutes
Hence, the saving manufacturing lead-time of Work center 10 from Setup A and B machine = 655 – 455 = 200 minutes
Source: (ORACLE, “ Oracle Bills of Material Users Guide”)
CALCULATION OF MANUFACTURING LEAD TIME OF WORK CENTER 20 FROM SETUP A MACHINE
Setup on A = 50 minutes is the preprocessing time
Processing time is the move time between operations i. e. 30 minutes
Post-processing time is the run time of A = 5 minutes per piece
Lot size = 125
Total post processing time = 5 x 125 = 625
Manufacturing lead-time = preprocessing time + processing time + post processing time
= 50+30+625 = 705 minutes
Source: (ORACLE, “ Oracle Bills of Material Users Guide”)
CALCULATION OF MANUFACTURING LEAD TIME OF WORK CENTER 20 FROM SETUP B MACHINE
Setup on B = 100 minutes is the preprocessing time
Processing time is move time between operations i. e. 30 minutes
Post processing time is the run time of B = 7 minutes per piece
Total post processing time = 7x 125 = 875
Manufacturing lead time = preprocessing time + processing time + post processing time
= 100+30+875 = 1005 minutes
Hence, the saving manufacturing lead-time Work center 20 from Setup A and B machine = 1005 – 705 = 300 minutes
Total saving manufacturing time of Center 10 and 20 from setup machine A and B = 500 minutes i. e. (200 + 300) minutes
Source: (ORACLE, “ Oracle Bills of Material Users Guide”)
6. 13. If the second machine is setup after the completion of the setup of first machine, then there will be no reduction in manufacturing lead-time. Setup time i. e. preprocessing time is fixed for a machine to work for a scheduled time. The manufacturing lead-time is affected with processing time i. e., move time between operations and post-processing time i. e. run time of the machines (ORACLE, “ Oracle Bills of Material Users Guide”).
6. 15. INPUT/OUTPUT REPORT AND ACTUAL BACKLOG AT THE END OF PERIOD 5
CUMULATIVE VARIANCE AND BACKLOG
Actual backlog is the differences between the total and actual planned within the given period. The calculation is done to maintain the output level for each period in order to reduce the lead-time and queue hours. The above report shows a lower level of input and output. The work centers performance can be monitored through the analysis of planned and actual outputs. The lead-time and queue performance are monitored through planned and actual backlog (Arnold 515). Based on the above interpretation, it is estimated that actual backlog at the end of period 5 is 37 units.
6. 16. DETERMINATION OF RUN SEQUENCE FOR EACH OF THE SEQUENCING RULES
First Come First Serve (FCFS) is a sequencing rule based on which a process or job, which arrive first for manufacturing and scheduling of products will be processed first (Pille 4).
Earlier Due Date (EDD) is the sequencing rule of a process or job in accordance with which due date period earliest from other due dates will be delivered first (Pille 4).
Operation Due Date (ODD) is the sequencing rule of a process or job on the basis of which operation due date earlier from other due dates will be operated first (Pille 4).
Short Processing Time (SPT) is the sequencing rule of a process or job based on which processing time shorter than other processing time are processed at the earliest (Pille 4).
6. 18. CALCULATION OF CRITICAL RATIOS AND ACTUAL TIME REMAINING (DAYS) FOR THE FOLLOWING ORDERS
Critical ratio is calculated by dividing the scheduled time of completion with the expected time of completion (Pearson Education 18).
Works Cited
Arnold, J. R. Tony. Introduction to Materials Management. India: Pearson Education India, 2011. Print.
“ ORACLE.” Oracle Bills of Material Users Guide. 2010. Web. Sep 19 2014.
Pearson Education. “ Operations Scheduling.” Scheduling Service and Manufacturing Processes (n. d.): 1-18. Print.
Pille, J. “ Memorandum.” Job Shop Sequencing Schedule (2013): 1-4. Print.

Thank's for Your Vote!
Chapter 6 homework. Page 1
Chapter 6 homework. Page 2
Chapter 6 homework. Page 3
Chapter 6 homework. Page 4
Chapter 6 homework. Page 5
Chapter 6 homework. Page 6

This work, titled "Chapter 6 homework" was written and willingly shared by a fellow student. This sample can be utilized as a research and reference resource to aid in the writing of your own work. Any use of the work that does not include an appropriate citation is banned.

If you are the owner of this work and don’t want it to be published on AssignBuster, request its removal.

Request Removal
Cite this Essay

References

AssignBuster. (2021) 'Chapter 6 homework'. 17 November.

Reference

AssignBuster. (2021, November 17). Chapter 6 homework. Retrieved from https://assignbuster.com/chapter-6-homework/

References

AssignBuster. 2021. "Chapter 6 homework." November 17, 2021. https://assignbuster.com/chapter-6-homework/.

1. AssignBuster. "Chapter 6 homework." November 17, 2021. https://assignbuster.com/chapter-6-homework/.


Bibliography


AssignBuster. "Chapter 6 homework." November 17, 2021. https://assignbuster.com/chapter-6-homework/.

Work Cited

"Chapter 6 homework." AssignBuster, 17 Nov. 2021, assignbuster.com/chapter-6-homework/.

Get in Touch

Please, let us know if you have any ideas on improving Chapter 6 homework, or our service. We will be happy to hear what you think: [email protected]